Lay thickness for a 2-in compacted lift (dense-graded, 25%)
Loose thickness to lay: 2.5 in
- Loose thickness: 2 in × (1 + 25/100) = 2.5 in
- Check: 2.5 in ÷ (1 + 25/100) = 2 in compacted
A 2-inch compacted lift does not start at 2 inches — crews lay it about 25% thicker (dense-graded, per the Asphalt Paving Handbook) and roll it down to spec. Convert either direction with an editable rolldown, and keep one rule absolute: this never touches your tonnage, which the square feet to tons calculator computes from the compacted number.
Loose = Compacted × (1 + Rolldown % ÷ 100) • Compacted = Loose ÷ (1 + Rolldown % ÷ 100)
| Symbol | Variable | Unit | Notes |
|---|---|---|---|
| L | Loose thickness | in | Mat depth behind the paver screed, before rolling. |
| C | Compacted thickness | in | Finished depth after rolling — the number tonnage uses, as the compacted vs loose asphalt guide explains. |
| R | Rolldown factor | % | ≈25% dense-graded, ≈15% gap/open-graded (Handbook §7-5). Editable for your mix and rollers. |
Every number below is produced by the same engine at build time — not typed by hand.
Loose thickness to lay: 2.5 in
Compacted thickness achieved: 2.5 in
The Asphalt Paving Handbook (§7-5) puts the common rolldown factor at approximately 25% for typical dense-graded mixes, and about 15% for gap/open-graded mixes. The factor is how much thicker the paver lays the mat than the compacted spec, so a 2-in compacted lift is laid about 2.5 in loose (2 × 1.25).
Dense-graded hot mix is laid about a quarter thicker than its finished compacted depth (a 25% rolldown), then rolled back to spec — the loose mat consolidates by roughly a fifth of its laid depth. The exact figure depends on mix design, lift thickness, temperature window, and roller type; measure your first lift to calibrate.
No — that is the most common ordering mistake. Tonnage comes from compacted volume × compacted density. The loose mat is the same weight spread thicker; multiplying tons by a compaction factor counts it twice.
Give them the loose thickness from the compacted → loose direction: target compacted depth × (1 + rolldown). Screed setups and grade strings are set to the loose number; inspection measures the compacted one.